Where does this stand now?
A three-phase expansion plan will be presented Feb. 9 to the Facility Design Development Committee
What is going to change?
1. Phase one: Add fields to the UREC Student Adventure Complex and an outside leisure pool to the UREC Student Recreation Complex
2. Phase two: Add a new wing to the UREC Student Recreation Complex
3. Phase three: Renovate the current Student Recreation Center, the main building within the complex
How much will it cost?
The total cost of the project is approximately $81.5 million
The project will be funded entirely by student fees
How would this affect you?
Students would see a fee increase of $45 each year
Students would not pay more than $200 in fees for UREC Student Recreation Complex expansion
UREC expansion plan in the works
January 19, 2012